We regularly receive requests for site contamination assessments for projects involving New York State Office of Community Renewal funding. One of the first questions we ask is:
How much OCR funding is proposed for the project?
People often ask why the funding amount matters.
The reason is that OCR’s documentation requirements change when a project will receive more than $100,000 in OCR grant investment. Above that amount, the Local Program Administrator must submit supporting documentation with the environmental professional’s site contamination certification.
That documentation might be a Desktop Environmental Review, Environmental Transaction Screen, Phase I Environmental Site Assessment, or another appropriate form of due diligence.
The funding amount helps us understand the documentation requirements, but it does not determine the appropriate assessment by itself. A project receiving more than $100,000 does not automatically require a Phase I ESA.
What does OCR require?
OCR’s Environmental Compliance Handbook states that covered project sites must be free of hazardous materials, contamination, toxic chemicals and gases, and radioactive substances that could:
- Affect the health or safety of occupants or users; or
- Conflict with the intended use of the property.
This does not mean that every property must have a perfect environmental history. It means potential concerns must be identified, evaluated, and appropriately addressed before project activities begin.
The evaluation must consider both the project property and nearby sites. A property’s current appearance does not always tell its complete story. A building that appears low-risk today may have previously been a gas station, dry cleaner, repair garage, manufacturing facility, or another use associated with petroleum or hazardous substances.
That is why the assessment includes both a site visit and a review of available environmental and historical records.
Unless a limited exemption applies, the site must be evaluated by an environmental professional. The environmental professional must either provide OCR’s required certification or recommend further investigation or corrective measures.
What changes when OCR investment exceeds $100,000?
For projects receiving more than $100,000 in OCR grant investment, the Local Program Administrator must provide backup documentation in addition to the environmental professional’s certification.
OCR identifies the following as examples:
- Desktop Environmental Review;
- Environmental Transaction Screen;
- Phase I Environmental Site Assessment; or
- Other appropriate supporting documentation.
OCR generally requires this documentation to be no more than one year old as of the funding application. If an older report is used, an environmental professional must confirm that it remains viable.
A Phase I ESA submitted for OCR review must comply with ASTM E1527-21.
These requirements are described in the NYS HCR/OCR Environmental Compliance Handbook.
How do we determine the appropriate level of review?
We generally use an escalating approach to site contamination due diligence:
- Desktop Environmental Review;
- Environmental Transaction Screen; and
- Phase I Environmental Site Assessment.
We conduct a site visit at every level. The difference is the depth of research, interviews, documentation, analysis, and reporting.
The starting point depends on factors such as:
- Current and historical property uses;
- Uses of adjoining and nearby properties;
- Conditions observed during the site visit;
- The proposed use of the property;
- Known spills, tanks, cleanup activities, or regulatory listings;
- The availability and quality of historical records;
- Whether the property is being acquired; and
- Requirements imposed by OCR, HUD, a lender, or another funding source.
Desktop Environmental Review
A Desktop Environmental Review is often a reasonable starting point for a property with a relatively simple, low-risk history.
Despite the name, our Desktop Review is not completed entirely from a desk. We visit the property, review reasonably available environmental databases and historical information, consider surrounding land uses, and compare the records with what we observe onsite.
When the property has a straightforward history, no concerning conditions are observed, and the available information is consistent, a Desktop Review may provide enough support for the environmental professional’s OCR certification.
A Desktop Review is not a defined ASTM assessment. If the property’s history is unclear or we identify something that cannot be resolved at this level, we may recommend further inquiry.
Environmental Transaction Screen
An Environmental Transaction Screen is a more structured form of limited environmental due diligence, generally performed in accordance with ASTM E1528.
It includes a site visit, a standardized environmental questionnaire, selected environmental and historical research, and inquiries about current and former property uses.
A Transaction Screen provides more structure and documentation than a Desktop Review but remains less comprehensive than a Phase I ESA.
It is generally best suited to properties that appear to have relatively uncomplicated histories but need a more formal level of screening. It may not be the best stopping point for a former gas station, dry cleaner, manufacturing facility, junkyard, landfill, or property involving substantial chemical or petroleum use.
A Transaction Screen also does not satisfy federal All Appropriate Inquiries requirements for CERCLA landowner liability protections.
More information is available in ASTM’s E1528-22 Transaction Screen overview.
Phase I Environmental Site Assessment
A Phase I ESA is the most comprehensive of these three levels. For OCR-funded projects, it must comply with ASTM E1527-21 and be completed by an environmental professional.
A Phase I ESA includes a detailed site visit, regulatory and historical research, interviews, evaluation of adjoining properties, consideration of potential vapor concerns, and a formal report containing the environmental professional’s findings and opinions.
Its primary purpose is to identify Recognized Environmental Conditions, commonly called RECs. In general, a REC involves the presence, likely presence, or material threat of a future release of hazardous substances or petroleum products.
A Phase I ESA normally does not include sampling. If a potential release is identified, the next step may be a Phase II ESA or another targeted investigation involving soil, groundwater, vapor, or indoor-air testing.
More information is available in ASTM’s E1527-21 Phase I ESA overview.
Why choose a Phase I when OCR might accept less?
A client may choose to proceed directly to a Phase I ESA even when OCR might accept a Desktop Review or Transaction Screen.
One of the primary reasons is liability protection.
A properly completed Phase I ESA can help a prospective purchaser satisfy federal All Appropriate Inquiries requirements and preserve eligibility for certain protections from liability for contamination the purchaser did not cause. A Desktop Review or Transaction Screen does not provide that same protection.
A Phase I does not automatically eliminate or transfer environmental liability to the consultant. It does provide a recognized and standardized level of due diligence, documents conditions known at the time of the assessment, and helps identify potential problems before a property is acquired or project funds are committed.
For an acquisition or another transaction where environmental liability is a concern, we often recommend proceeding directly to a Phase I ESA and discussing the results with the client’s attorney.
When does a review need to escalate?
Environmental due diligence is not simply a pass-or-fail process.
Sometimes a question can be resolved by obtaining one additional record or clarifying a former property use. In other cases, the available information indicates that a more comprehensive assessment is needed.
Common reasons for escalation include:
- A current or former gas station, dry cleaner, repair garage, or industrial use;
- Petroleum tanks or documented spills;
- Chemical storage or handling;
- Evidence of dumping, filling, or waste disposal;
- Nearby contaminated or regulated properties;
- Stained soil, unusual odors, drums, tanks, pits, or distressed vegetation;
- A proposed change to residential or another sensitive use;
- Missing or conflicting historical information;
- Areas of the property that could not be inspected; or
- A request for additional documentation from OCR or another reviewing agency.
Escalation does not mean contamination is definitely present. It means more information is needed before the environmental professional can reach a supportable conclusion.
When a project moves from one level to another, we use the site observations, records, and other information already collected wherever appropriate. Each level has its own requirements, so additional research, interviews, site observations, analysis, or reporting may still be necessary.
What happens if a potential concern is identified?
If the environmental professional cannot provide OCR’s required certification, further work must be completed as recommended.
Depending on the issue, that work might include:
- Additional historical research;
- Review of regulatory files;
- Tank or spill documentation;
- A Phase I ESA;
- A Phase II ESA;
- Soil, groundwater, vapor, or indoor-air testing;
- A corrective-action or remediation plan;
- Changes to the project scope; or
- Consultation with OCR or the HTFC Environmental Unit.
A recommendation for additional investigation is not a conclusion that the property is unsafe or unsuitable. It means a potential issue needs to be better understood and appropriately addressed.
Complete the environmental review before starting work
Environmental review should be addressed early in project planning.
OCR advises Local Program Administrators not to begin physical work or incur project costs before the site-specific environmental review has been submitted and the required environmental determination has been received. Costs incurred too early may be ineligible for reimbursement.
Starting early leaves time to obtain missing records, answer agency questions, complete additional investigation if necessary, and incorporate required measures into the project scope.
OCR does provide a limited exception for certain minor exterior-only projects costing $10,000 or less when there is no interior rehabilitation, ground disturbance, or new construction. The full scope and cost must be reviewed before assuming that an exemption applies.
What if the project also has HUD funding?
HUD-funded projects have federal environmental review requirements in addition to any applicable OCR requirements.
A Desktop Review or Transaction Screen accepted for an OCR-funded project should not automatically be assumed to satisfy HUD. The HUD program, property type, number of dwelling units, proposed activities, property history, and level of environmental review can all affect what is required.
A Phase I ESA also does not complete the entire HUD environmental review. Floodplains, historic resources, wetlands, noise, radon, lead-based paint, and other environmental topics may need to be addressed separately.
This is why we ask about every anticipated funding source before recommending a scope.
Not sure where to start?
Send us the property address, proposed scope of work, amount and source of public funding, current and former uses if known, project schedule, and any previous environmental reports.
We can review the available information, recommend an appropriate starting point, and explain what circumstances could require additional investigation.
This article provides general information and is not legal advice, a regulatory determination, or a guarantee of agency acceptance. Environmental requirements, program guidance, and ASTM standards may change. Individual projects may be subject to additional requirements.